Monday, September 07, 2009

THE SAGA CONTINUES

23 Sept 2009: Charter flight landed in MYQ Airport carrying tourists on the Dasara trail. I hope the service lasts beyond Dasara, and hope that if such is the case, the DGCA will complete its certification works of the Airport and we can look forward to long lasting service. I hope I am not overly optimistic!

LATEST NEWS AS ON DATE; 21 SEPTEMBER 2009:

I am not sure how long this link to Star of Mysore archives will be available online. In short, it says that Mysore Airport Inauguration has been put off indefinitely. There is going to be nothing happening for a while. There are no flights announced and none planned by any Airline, hence no one interested in opening an empty airport. All we have are false assurances from various authorities and ministers. SOM report claims that all that is false. Saga continues....
Star of Mysore link: http://starofmysore.com/main.asp?type=news

SCROLL DOWN TO READ UPDATES PREVIOUS UPDATES.

MAIN ARTICLE:

OK, here is a bit of disappointing news, if true. Indian Express online today says that the Directorate General of Civil Aviation is not going to visit Mysore and conduct inspection before Dasara. They do not have the time to conduct this detailed and elaborate inspection at this time. The earliest inspection may be done sometime after December.

What does this mean to you and me? Well, nothing much really, no Airline had come forward to operate to and from Mysore to any point anyway. Global Vectra Helicopters had made a statement that they would like to operate a helicopter service. Well, that's going to be too bloody expensive, pardon my French.

Now, to save face, the State Government may still go ahead and inaugurate the Airport. Since it won't mean much, the same can be symbolic. Let us Mysoreans take it on the chin, again. Can they run the Airport without DGCA permissions? Of course they can, like they used to on the grass strip that existed before, minus the Control Tower of course, maybe minus the Meteorological service for the operators (if any operator, that is), minus fueling (that facility isn't even ready), minus fire fighting services (God, I hope not).

Well, here is the silver lining: Sources have been quoted saying that the State can still operate chartered flights "at it's own risk" even if DGCA clearance is not done before Dasara. That's how chartered flights used to fly into Mysore in the past. What a tangled web we weave. This is like someone playing April fools day in September. Fingers crossed and hope to fly!

UPDATED 19 September: No charter flight into MYQ Airport! What happened? Sri Sri Ravishankar arrived by Road to inaugurate Dasara. The Chief Minister arrived by Helicopter and landed at Lalitha Mahal Helipad. No one came in any chartered Kingfisher Aircraft like it had been announced before!

UPDATED on 16 September: Latest report says the Chief Minister and his entourage and Sri Sri Ravishankar and entourage are going to be landing at the new Mysore Airport (MYQ) on the 19th of September in a chartered ATR Aircraft. However, this will be a one off flight and is not the real inauguration of the Airport. The "official" inauguration may be on the 22nd of September when Civil Aviation Minister Praful Patel visits Mysore. Don't know how far this is true either. Earlier report spoke of the PM visiting and inaugurating the Airport.

Latest from Mysore's paper says that Kingfisher will fly between Bangalore and Mysore in an ATR 42 (50 seat) between 22nd and 26th of September. Kingfisher will then start weekend services from Mysore to other destination such as Mumbai, Hyderabad, Chennai and Goa! Have they been reading my blog? hehehe...

Monday, July 20, 2009

MYSORE AIRPORT LATEST AS ON JUL 2009

Hi All, for those of you who have been following the story on my blog about Mysore airport, here's the latest. I was in Mysore recently, just a few days back and found that the tarmac and runway is ready at the Mysore Airport. There have been some chartered flights that have already operated in and out of the Airport on unscheduled visits, having obtained prior special permission to land at Mysore. For those who live in Mysore or have been reading some sites on the net, they would already know this information. For those who don't have the latest, here is what's been going on.

The last item for development before the Airport can be officially opened is the terminal building. As it appears, the work is going on in full swing. Credible reports from the current DC of Mysore Mr. Manivannan suggests that the Airport will be open in time for Dasara 2009. That's around the last week of September this year. Some readers may laugh at this because several Dasara festivals in Mysore have come and gone with politicians of every hue and color making statements that the Airport would be ready by Dasara time. This time, it may be believed because the statement comes from the DC of Mysore, a person who I credit all positive things that are happening there. If there is an honest, upright and dynamic officer, then Manivannan is the man and he has been an asset to Mysore notwithstanding the political pressures that his office may experience and the threat of transfers of such good officers, again coming from politicians of every hue and color.

So after much waiting, decades of it in fact, maybe we are seeing the light at the end of the tunnel. Naysayers are still at work saying that the Airport is inadequate, large Aircraft cannot operate from them and that additional land needs to be acquired, this is not the end of the story..blah..blah...blah.

It is left to the operator to decide whether there is enough traffic from Mysore for large Aircraft and if so, what sectors would make sense and so on. Airline business is not a charity, it is highly sensitive and break even/loss making at the best of times. To speak of the current situation where load factors on known, established routes have come down drastically and every one painting red on their Balance Sheets, one cannot expect anything more from the industry. The point is, at last we have an airport that can see commercial operations. Let's hope it is viable for operators to come in with ATR turboprops to begin with. Let's see what sectors will be offered and whether those sectors make enough sense in the long run for the operator to stay on this route. If the viability fails, it does not matter how big the Airport is or what it can handle in terms of Aircraft. If viability fails, we will have an airport either with sporadic service or none at all. Lets hope this becomes viable in the long term and it appears that way at the moment. I, for one, will await with some eagerness, to see the day we have air services into Mysore. Hopefully it is in September this year!

Sunday, December 23, 2007

MYSORE AIRPORT – LATEST NEWS AND UPDATE

In December 2005 – two years ago, I wrote about the plan that the Airport Authority of India was making, to construct a regular airport in Mysore, India, my home town. Later on in April and May 2006 I followed up this story and made critical comments on how the airport project was making sound bites of the wrong kind and how the local media wasn’t getting it right either. As promised in my blog of April 2006, I am updating the news in my new blog that I use for writing only on aviation and aviation related matters.

I am late in updating news and that has been due to a combination of the fact that the much announced and much awaited (20 years or more in the waiting!) project ran into troubles from the start and also because I could not gather any information on the progress, if there was any, of the project because I was away overseas for all this time and no news or data was available on the internet about this airport. If you the reader attempt to research this airport on the internet, you’ll just come up with links to my blog and articles I had written last year on other online aviation magazines.

Well, I’m glad that this time I made it to Mysore on a very brief trip and managed to go to the construction site to see for myself what was going on. I had met the Airport Director of the Bangalore International Airport before heading down to Mysore and had a fair idea of how things had progressed in the time I was gone and since the days of my first writing on the subject two years ago. The Director had been candid about the problems they had faced and the commitment they had for the project that kept it going nevertheless.

(The present "terminal")

Here are some pictures of the Airport, a Second World War surplus airfield, with a grass strip that was once used to fly DC-3 Aircraft and trainer Aircraft such as the Famous biplane the Tiger Moth. These pictures at least give the impression of activity going on at the Mysore Airport. What I saw while I was there seemed impressive, truck loads of material was seen arriving every five minutes, material that would be used at the site. The main runway to cater initially for ATR-72 type Aircraft (68 passengers) is being completed. This will be extended in the second phase to accommodate larger Aircraft such as the Airbus A320/Boeing B737 types. When it gets done in the first phase, it will be a great place for companies to set up light Aircraft/corporate Aircraft maintenance and a flight school and the latter seems to be an idea that may be already in the pipeline, from an undisclosed private party.

(Path from the tarmac area towards the old terminal building)

What I could see is that their first goal of laying the runway was almost over and this is to be followed up by putting in the taxi ways, tarmac area and the airport terminal building. What you see in this picture is the original old “terminal” building that used to be operational even 20 years ago when Vayudhoot (a commuter airline those days) operated a Dornier 228 to and from Mysore using the grass runway. The present estimate for completion of the project is October of 2008 and the officials are confident of meeting this deadline. I’m planning on a trip out to Mysore Airport again sometime in May/June of next year. I’ll update the news on the developments and I’ll encourage Mysoreans to keep their fingers crossed in the meantime and hope that the Airport will be opened soon; it will bring a sigh of relief to the locals.

(construction equipment working on the main runway)


Happy Holidays and Happy 2008 to all, may everything that you aspire for, come true next year. Cheers.